Project timetable

Find out what is happening and when on the Major Housing Project

Timetable of events

The intention will be to develop the sites in the sequence below. Planning permission for the new road was granted on 10 April 2015.

The following timetable outlines the proposed dates when planning applications for individual sites are expected to be submitted, but these may be subject to change.

Housing site         Planning reference     Planning application
submission date  
      
Decision expected         Date on site        
Marsh Lane 15/00828/FM May 2015  December 2015 April 2016
Lynnsport 3 16/00097/FM January 2016 June 2016 2017
Lynnsport 4 16/01327/FM June 2016 December 2016 TBC
Lynnsport 5 16/01327/FM June 2016 December 2016 TBC
Lynnsport 1 Due December 2016 December 2016 2017 TBC

The following timetable outlines key dates for works taking place on the Green space & Alive Lynnsport facilities, but these may be subject to change

Site Date on site Estimated completion
Hockey pitches and tennis courts   November 2015 Complete July 2016
Miniature railway relocated March 2016 Completed November 2016
New road and car parks March 2016 December 2016
Dutton Pavillion Extension December 2017 TBC

Planning applications received by the Planning Department will be available to view on our planning pages. Comments on applications can be submitted online using the same link.

We will be organising further consultation events for each housing site, prior to submission of the planning application, and once the planning application has been submitted. Consultations will be published on our Have Your Say page on this website and will be announced in the media and via twitter @WestNorfolkBC.